Let me share with you how exciting it is for me to see the Secondary School become a Hope Made Real.
This is the view that will be seen every day from the Secondary School complex. Awesome!
I would like to join Benjamin, but it looks a bit scary to me.
A Jan. 29 update on Secondary School progress: Ready for inspection. Government inspectors are on site this morning. We need their approval before we can go ahead.
Approval given. Yay!!!
Work began on the upper retaining wall.
Feb. 4. Work continued.
Feb. 16. Upper retaining wall is finished.
Pillars for support of a two-story building. There are many – about 12.
To my amazement, we have a cement mixer. Not the big truck like in the USA, but it works.
Foundation going in. The pillars are encased in cement and are included in the foundation.
Feb. 26. Progressing.
Our director Jean Marie donned a vest and helmet to inspect the work in progress.